Numerical Ability · Word Problems · Lesson
Work problems
Turn each worker's time into a rate, add the rates when they work together, then divide the job by the total rate.
The idea
A work problem asks how long a job takes, or how much gets done, when one or more people or machines work at a steady pace. The key idea is the rate: how much of the job is done in one unit of time.
If a painter can paint a room alone in 6 hours, the painter's rate is 1/6 of the room per hour. If a second painter needs 3 hours, that rate is 1/3 of the room per hour. When they work together, their rates add, not their hours. Together they paint 1/6 + 1/3 = 1/2 of the room each hour, so the room takes 2 hours.
The same pattern holds for pipes filling a tank, printers making copies, or machines packing goods. Work = rate × time, so time = work ÷ rate.
How to do it
- Call the whole job 1.
- Write each worker's rate as 1 ÷ (time to do the job alone).
- Working together: add the rates. If one undoes the work, such as a drain, subtract its rate.
- Time together = 1 ÷ (total rate).
- For exactly two workers, a shortcut works: time together = (a × b) ÷ (a + b), where a and b are their times alone.
Worked example
A clerk can encode a batch of forms in 4 hours. A second clerk can encode the same batch in 12 hours. Working together, how long do they take?
Step 1. Rates: the first clerk does 1/4 of the batch per hour, the second does 1/12.
Step 2. Use twelfths: 1/4 = 3/12, so together they do 3/12 + 1/12 = 4/12 = 1/3 per hour.
Step 3. At 1/3 of the batch each hour, the whole batch takes 3 hours.
Step 4. Shortcut check: (4 × 12) ÷ (4 + 12) = 48 ÷ 16 = 3.
Answer: 3 hours.
An inlet fills a water tank in 6 hours. An open drain alone would empty the full tank in 15 hours. If both are open, how long does the empty tank take to fill?
Step 1. Inlet rate: 1/6 per hour. Drain rate: 1/15 per hour, working against the inlet.
Step 2. Use thirtieths: 1/6 = 5/30 and 1/15 = 2/30. Net rate: 5/30 - 2/30 = 3/30 = 1/10 per hour.
Step 3. At 1/10 of the tank each hour, the full tank takes 10 hours.
Answer: 10 hours.
Five masons build a wall in 8 days. Working at the same pace, how many days would 4 masons need?
Step 1. The job is 5 × 8 = 40 mason-days.
Step 2. With 4 masons: 40 ÷ 4 = 10 days.
Answer: 10 days.
Watch out
- Never add the times. Two workers together are always faster than the faster one alone. If your answer is longer, you added hours.
- A drain or an outlet works against the job, so you subtract its rate.
- For crews of the same workers, use worker-days: more workers means fewer days, so divide.
- Use a common denominator, the smallest number both times divide into, to keep fractions easy.
Remember
- Rate = 1 ÷ time alone.
- Together, add the rates.
- Time together = 1 ÷ total rate.
- Two workers: (a × b) ÷ (a + b).
- Crews: workers × days stays the same.
Practise it
Answer Word Problems questions one at a time and read why each answer is right.
Practise this in r3viewMore Word Problems lessons
- Word problems, the overviewName the unknown, write a short equation from the facts, solve it, then check that you answered the question asked.
- Distance, speed and timeDistance equals speed times time. Match the units, and use the sum or difference of speeds when two travelers move.
- Age and number problemsThe age gap between two people never changes. Use a now-and-later table, and let one letter stand for the unknown.
- Mixture and average problemsAn average is a sum divided by a count. Work with the sum, and treat mixtures as a weighted average of their parts.
- Money problems, discounts and interestTotal cost is price times quantity. Take discounts one at a time, and find simple interest with principal times rate times time.
Word Problems: rule, key facts and questions with answers
Sources
- Method r3view team method
Written by the r3view team and checked by an admin before it went live. Updated . r3view is not affiliated with the Civil Service Commission.